Difference between revisions of "18 Assigning Steps"
From TrueERP wiki
Simon Clive (Talk | contribs) (Created page with "Assigning Steps How do you add a Process_Step<LinkId=973> to a sub-branch? Each item in a BOM must have its own branch with its own process steps and input types. A branch can ...") |
(No difference)
|
Revision as of 14:20, 29 June 2011
Assigning Steps
How do you add a Process_Step<LinkId=973> to a sub-branch?
Each item in a BOM must have its own branch with its own process steps and input types. A branch can be off the main tree or it can be a branch off a branch (sub-branch).
How to add a Process Step
Select Inventory Select Product Select Manufacturing Select the Process Steps field in the sub-branch Select a Process Step from the drop down list Enter the Duration<LinkId=984> or time required for the step as well as any setup and breakdown time Enter the Sequence<LinkId=985> number if more than one step (if not leave the default value)