Defining Capacity
+
'''Defining Capacity'''
  
Can you define the capacity for a resource?
+
Can you define the capacity for a resource?  
  
A Production_Resource<LinkId=974> can be a person, a piece of equipment or a workspace. Work Processes are allocated to a  
+
A '''Production Resource''' can be a person, a piece of equipment or a workspace. Work '''Processes''' are allocated to a '''Resource''' which ensures that processes are not scheduled at a time when there are insufficient resources to complete them.  
resource which ensures that processes are not scheduled at a time when there are insufficient resources to complete  
+
them.
+
  
How to Define Capacity
+
*To define '''Capacity''' select the '''Manufacturing''' Module and then select the '''Resource List''' to view/edit an existing resource  
 
+
*Enter under '''Capacity''' the total number of hours the resource is available per day '''Eg.''' If the resource is '''Welding Bays''' and there are four employees working in the welding bays for eight hours per day, the capacity is '''4 x 8 = 32'''
Select the Manufacturing tab
+
*If there are daily '''Setup times''' or '''Breakdown times''' for the resource subtract these from the figure above.
Select the Resource List to view/edit an existing resource
+
Enter under Capacity the total number of hours the resource is available per day. eg. If the resource is "Welding
+
Bays" and there are four employees working in the welding bays for eight hours per day, the capacity is 4x8=32
+
If there are daily setup times or breakdown times for the resource (not each job) subtract these from the figure  
+
above.
+

Latest revision as of 14:50, 29 November 2011

Defining Capacity

Can you define the capacity for a resource?

A Production Resource can be a person, a piece of equipment or a workspace. Work Processes are allocated to a Resource which ensures that processes are not scheduled at a time when there are insufficient resources to complete them.

  • To define Capacity select the Manufacturing Module and then select the Resource List to view/edit an existing resource
  • Enter under Capacity the total number of hours the resource is available per day Eg. If the resource is Welding Bays and there are four employees working in the welding bays for eight hours per day, the capacity is 4 x 8 = 32
  • If there are daily Setup times or Breakdown times for the resource subtract these from the figure above.