Personal tools

2 Weeks to Display

From TrueERP wiki

Revision as of 09:43, 29 November 2011 by Simon Clive (Talk | contribs)

Jump to: navigation, search

Weeks To Display

Have you defined how many weeks in advance that you wish to display the calender?

The number of weeks to display is largely dependent on the amount of time taken to process orders.

From the Main Menu select How to Set Product Source Go to Utilities Tab Select Preferences Select Manufacturing Under the heading Production Planning, enter the number of days

Auto Scheduling

Under the heading Auto Scheduling, set the number of Auto Production scheduling Grace Days. This is how many days from when the order is placed until you need to schedule it. You can set the number of grace days to Forward. eg. Forward 1 day means the order will be scheduled for production 1 day after the order is placed. Alternatively you can set the number of grace days Reverse. eg. Reverse 1 day means the order will be scheduled for completion 1 day prior to the shipping date

Stock Requirements Under the heading Stock Requirements set how many days ahead do you need to order stock prior to production being scheduled